SialkotWebAbout SialkotNewsWeatherSialkot Int'l AirportSialkot Lahore MotorwayUESTP-Engineering UniversityForumChatPhoto GalleryHoroscope

 

 

SIALKOTWEB HOME

 

About SIALKOT

o     Introduction

o     Geography

o     Economy

o     Government

o     History

o     Tourism

o     Development

o     Pictures

 

SIALKOT INT'L AIRPORT

o     Introduction

o     Features

o     Pictures

 

Sialkot Lahore Motorway

o     Introduction

o     Route Map

o     Features   New

 

UESTP-(University of Engg,                  Science & Technology)

o     Introduction

o     Educational Activities

o     Goals & Objectives

o     Location Plan

 

SIALKOT NEWS

 

WEATHER

 

FORUM DISCUSSION

 

ONLINE CHAT

 

MAPS of SIALKOT

 

DAILY HOROSCOPE

 

                  IntroductionRouteFeatures  

SIALKOT LAHORE MOTORWAY - BRIEF

 

 

BRIEF - updated

 

 

100 Km Sialkot--Lahore Motorway,

a divided six lanes limited access facility alongwith

Daska Bypass (11.85 Km) and

M-2 Link (8.81 Km).

i)

Interchanges

08 Nos

ii)

Flyovers

03 Nos

iii)

Bridges.

50 Nos

iv)

Bridge over River Ravi

01 Nos

v)

Underpasses

80 Nos

vi)

Drainage Culverts

120 Nos

vii)

Water Courses Culverts

100 Nos

b)

Universities

2 Nos.

c)

Imdustrial Zones

3 Nos.

d)

New Commercial Areas.

e)

Operation and Maintenance from Toll and Commercial Activity.

 

 

CHARACTERISTICS:

 

The project being of a huge magnitude is given under the Project Management unit which will ensure implementation of the project through state-of-the-art management methods.

 

Sialkot-Lahore Motorway,

 

Start Point:  Sambrial dry port at 22 km from Sialkot and close to Sialkot International Airport.

 

Lanes: A divided six lanes limited access facility.

 

Length: 100 Km

 

Travel Time: 1 hour

 

End Point: East side of Lahore Ring Road & Niazi Interchange

 

 

MAJOR PROJECTS ALONG MOTORWAY

 

UESTP (University of Engineering & Technology Pakistan with collaboration of KTH)

German University

Three Industrial Estates at Daska, Gujranwala, Lahore

Sports City at Lahore

IT Park

Lake City

 

NESPAK has been awarded contract for:

 

Project Planning

Detailed Design

Tender Documents &

Construction Supervision

 

Project Cost & Implementation:

Total Project cost is estimated upto PKR 23.00 bn

Estimated Engineers cost for the project is PKR. 22.0 Billions.

Detailed Engineering Services will be 1.84 %,

Construction Supervision will be 2.0 % of the cost of Civil Works.

 

Detailed Engineering design completion schedule is 12 months

Proposed project Completion period is 2-1/2 years (30 months)